Report on the 6th Working group Meeting of the eProcurement Ontology
This report is also available as DOCX, ODT and PDF
formats.
Project: |
eProcurement Ontology |
Meeting Date/Time: |
2018-05-16 15:30 – 17:00 |
Meeting type: |
6th Working Group Meeting |
Meeting Location: |
Videoconference Webex https://ecwacs.webex.com/meet/nmuric |
Chairperson: |
Natalie Muric |
Issue Date: |
2018-05-16 |
Meeting Agenda |
·
Presentation of the participants ·
Conceptual data model ·
Development of the PoC ·
Any other business |
List of Participants |
||
Attendee Name (present) |
Initials |
Organisation / Email |
Laia BOTA |
LB |
everis |
Patrizia CANNULI |
PC |
IT Consip |
Oscar CORCHO |
OC |
Universidad Politécnica de Madrid |
Manuela CRUZ |
MC |
OP |
Maria FONT |
MF |
everis |
Cécile GUASCH |
CG |
ISA2 Contractor |
Natalie MURIC |
NM |
OP |
Enric STAROMIEJSKI |
ES |
everis |
Summary of Meeting |
Presentation of
the Participants The participants of the meeting presented themselves (see list of
participants – in alphabetical order). Glossary
feedback and expectations from WG Currently, there is not feedback related to the Glossary. However, technical
weekly meetings will be set up in order to: ·
Get feedback and discuss about the definitions and
terms from the glossary; ·
Review the coherence in both technical and
business points of view; ·
Review the progress on design and implementation
topics (e.g. n-ary relationships between classes,
model documents as classes, etc.). Conceptual data
model The working group was informed on the progress of the ePO v2.0.0 conceptual data model: 1.
The process when developing the conceptual data
model diagrams is: first the OP reviews the diagrams and afterwards,
explanatory sentences are added in order to make them more understandable. 2.
The diagrams are going to be published in the GitHub,
so the WG can see them and cooperate with the development. 3.
The TTL file is developed using Protégé and taking into account the
conceptual data models. Any questions related to the conceptual model should be added as issues
in the GitHub space. Development of
the PoC According to the methodology
of the PoC, the current status is working on the development of the ETL process
(extraction, transformation and loading). A dataset has been downloaded from TED portal. There is a previous analysis before the transformation between TED XML
to ePO. The mapping between these two data
structures have four different possibilities: ·
TED XML element exists in the ePO.
This is a direct mapping. ·
If TED XML element exists in the ePO but it is expressed differently, the transformation
need to process this mapping. ·
If an ePO element does
not exist in the TED XML, there is no mapping. ·
If a TED XML element does not exist in ePO, this situation needs to be reanalysed, and this
could modify the ontology or not. The results of this mapping are expressed using SPARQL queries. ·
The triples
produced from the transformation are inserted in GraphDB
as a result of the queries. The ETL process is executed automatically using a Java application. Future meetings
are planned: 14/06/2018 ·
Revision of the ontology, OWL implementation and
results of the PoC The work to be presented in each meeting will
generally be made available for the working groups’ information approximately
one week before each meeting. |
Proposed
Agenda for Next Meeting: |
Proposed Next Meeting
Date: |
2018/06/14 |
I.
Conceptual data model II.
Results of the PoC III.
AOB |